bathroom remodel – we have a functional tub!!

From start to finish (signed paperwork on September 1st 2021 to the tub filler being installed on April 26th 2022) it took 237 days for ReBath to do all their work and at least their bit is done.

The long pole item was the floor standing tub filler and it finally got installed yesterday. We were told that Delta shut down production during the worst of the pandemic and that is what caused the months and months of waiting. :shrug:

Regardless, it’s in and functional.

Still on the docket to be completed;
– patching the ceiling,
– painting the ceiling, walls, and baseboards,
– there are built in medicine cabinets and a magazine holder that need some sanding and painting
– some kind of window treatments
– and finally the shower glass